A 3D energy model of our VURB project at Hillwood

Hillwood

Through VURB pathway, glazing cost was reduced by increasing U-value from U3.3 to U3.6. This was achieved by adding 30% more insulation to the walls and 14% more insulation to the ceilings.

Please click here for more details on VURB Performance Solution.

Feel free to navigate through dozens of our similar projects below:

2023-02-14T03:01:10+00:00

Legana

In this project, using our solutions the client managed have overall Window U-value of U3.4 instead of U2.6 (more than a 30% increase).

2023-06-19T05:23:59+00:00

Westwood

Adding 50mm rigid insulation to the slab and filling ceiling and wall void spaces with insulation, we managed to increase overall window U-values from U2.0 to U3.8 and significantly save construction costs.