Project Description

Glazing cost was reduced by increasing averaged U value from 4.5  to 5.2. This was achieved by adding 47% more insulation to the floors and 36% more insulation to the ceilings.
Proposed commercial building (class 9b) is located in the city of Promised land.
Through JV3 Performance Solution method, we managed to reduce overall glazing U-value by more than 15%.
Here are some more details on the degree of insulation and glazing thermal performance for the Promised land project:

Item NCC 2016 Reference Building Proposal Building
Suspended Floor R1.7 added to the suspended floors R2.5 added to the suspended floors
Internal and common walls No insulation added to the internal walls. No insulation added to the internal walls.
External walls R2.52 added to the external walls R2.5 added to the external walls
Roof/Ceiling R3.31 added to the ceilings of all external roofs R4.1 added to the ceilings of all flat roofs.
R5.4
added to the ceilings of all pitched roofs.
External shading Shading from other buildings and external eaves and shading have been implemented into the analysis based on available drawings. No new shading proposed
Glazing All east facing windows:
U-Value: 3.0, SHGC: 0.15
All other facing windows:
U-Value: 6.0, SHGC: 0.53
All windows:
U-Value: 5.2, SHGC: 0.43

If you would like to save on your building construction costs, contact our team at Energy Compliance and one of our friendly staff will discuss the opportunities to save in your costs. Energy Compliance offers a unique service guarantee:
If we can’t reduce your construction costs by more than twice the value of our service fee, and you decide not to use our report, then you won’t have to pay the remainder of our invoice.


Get a quote

Similar projects: