Templestowe

Through JV3 modelling, construction cost was reduced by keeping existing walls from new works (insulation). This was done by decreasing averaged U value from U4.0 to U3.9 and by adding 120% more insulation to the ceiling.

Please click here for more details on JV3 Performance Solution.

Feel free to navigate through dozens of our similar projects below:

2023-02-14T04:14:04+00:00

Southbank

Through JV3 assessment, the proposed building existing curtain walls were kept from changing and also, new curtain walls were kept clear with high SHGC

2022-12-23T08:55:49+00:00

Sherwood

Through JV3 assessment, we were able to obtain energy compliance for the new extension by adding minimum 1kW solar PV to the proposed building.